296-298 Kings Road, Chelsea
Main Contractor: Total Construction Ltd
Value of Works: £760k
Overview:
Works involved the complete refurbishment of an existing Public House to give a mixture of residential and retail spaces. Our contract included temporary works, demolitions and construction of a large basement below the existing footprint of the property.
Scope of Works:
Demolition and strip out; Temporary works installation/removal; Underpinning – reinforced concrete; Underpinning – mass concrete; Bulk excavation and disposal; Underground drainage; Installation of pump chambers; Substructure concrete works; Formwork; Reinforcement.
Programme period: 26 weeks
Completion date: June 2017